Development of Salalah International Airport Main Contract – 5

Scope of Work:

Engineering, Procurement and Construction of new 4 Km Runway, Taxiway & Aprons including Airfield Lighting System, Landside Roads & Bridges, Airside Roads with Perimeter Security Fencing, Air Quality & Noise Monitoring system, Stormwater Drainage network, Landscaping with Irrigation network, Landside Traffic Management System with covered Car parking of 3,000 Nos including Intersections, Roundabouts and Road Signage’s

  • Landside and Airside Roads – 40 Km
  • Stormwater Drainage
  • Wadi Bridges – 4 Nos

Client

Ministry of Transport & Communications

Project Value

RO 101 Million

Duration

2010-2017